    Brown out issues

    During some summer thunderstorms, my Apex setup ( Apex, AWM, break out etc) has not rebooted cleanly, leaving the ATO running but the lights off. Even with a Fallback OFF on the ATO outlet, the pump has kept running almost overflowing the tank. The brownout wasn't enough to trigger various network equipment. I've installed a UPS to ride through these outages but is there a reason why the Apex won't reboot cleanly and take control of everything? Latest firmware etc...

  2. #2
    Master Control Freak aquamanic's Avatar
    Join Date
    Jan 2013
    Location
    Baton Rouge, LA
    Posts
    6,181
    Your ATO pump might be too small to shut-off properly. What kind of pump and what outlet # is it running on?
    Al

    I do not work for Neptune. Please do not send me PMs with technical questions or requesting assistance - use the forums!
    For Neptune support send an email (don't call) to: [email protected] .
    Manuals for all products including the
    Comprehensive Reference Manual can be found here.

  3. #3
    Regular Vistor
    Join Date
    Jan 2015
    Location
    USA
    Posts
    24
    That had crossed my mind. It's on a triac outlet of an EB8 and is an Innovative Marine Hydrofill. It switches on and off fine when everything is working correctly. I could move it to a relay output.

  4. #4
    Master Control Freak aquamanic's Avatar
    Join Date
    Jan 2013
    Location
    Baton Rouge, LA
    Posts
    6,181
    Looks like it draws 10w. That's not a lot but should be enough for a Triac.

    Can you post your ATO code?
    Al

    I do not work for Neptune. Please do not send me PMs with technical questions or requesting assistance - use the forums!
    For Neptune support send an email (don't call) to: [email protected] .
    Manuals for all products including the
    Comprehensive Reference Manual can be found here.

  5. #5
    Regular Vistor
    Join Date
    Jan 2015
    Location
    USA
    Posts
    24
    Fallback OFF
    Set OFF
    If Depth CLOSED Then ON
    If Depth OPEN Then OFF
    If Overfl OPEN Then OFF
    If Leak_L CLOSED Then OFF
    If Leak_R CLOSED Then OFF

    I have just added the initial Set OFF and the last two leak detection lines (more for completeness than anything else). I was hoping the Fallback OFF would be enough to ensure the ATO wouldn't kick in upon partial reboot.

  6. #6
    Master Control Freak aquamanic's Avatar
    Join Date
    Jan 2013
    Location
    Baton Rouge, LA
    Posts
    6,181
    I have just added the initial Set OFF
    That may have been all it needed. Except in a few cases you almost always need a Set statement to establish a baseline for the rest of the program.
    Al

    I do not work for Neptune. Please do not send me PMs with technical questions or requesting assistance - use the forums!
    For Neptune support send an email (don't call) to: [email protected] .
    Manuals for all products including the
    Comprehensive Reference Manual can be found here.

  7. #7
    Regular Vistor
    Join Date
    Jan 2015
    Location
    USA
    Posts
    24
    Quote Originally Posted by aquamanic View Post
    That may have been all it needed. Except in a few cases you almost always need a Set statement to establish a baseline for the rest of the program.
    Ok and Thanks. I'll see how it works out. With an incomplete boot (the status light was flashing , not solid green), I'm guessing the EB8 was left in an inconsistent state. I always thought the fallback off would take care of that but I have a lot to learn about the Apex. With the set off and the UPS installed, hopefully I won't have anymore near over flows.

  8. #8
    Master Control Freak aquamanic's Avatar
    Join Date
    Jan 2013
    Location
    Baton Rouge, LA
    Posts
    6,181
    Your understanding of Fallback is correct - if the EB is flashing yellow it means it can't communicate with the controller. In that case it will set outlets to their fallback state. However, once communications are resumed, fallback is ignored and the program takes over. In your case, there was nothing to define a starting point for the outlet. If every possible on condition had an associated off or vice versa, it wouldn't be a problem.
    Al

    I do not work for Neptune. Please do not send me PMs with technical questions or requesting assistance - use the forums!
    For Neptune support send an email (don't call) to: [email protected] .
    Manuals for all products including the
    Comprehensive Reference Manual can be found here.

Similar Threads

  1. Help! Calibation issues
    By Scubalens in forum Misc Apex Usage & Programming
    Replies: 1
    Last Post: 02-14-2019, 18:45
  2. Issues...please help
    By flounder in forum Apex Classic/Apex Lite/Apex Jr
    Replies: 5
    Last Post: 07-05-2017, 08:56
  3. Help! PH Issues
    By Stylo328 in forum Apex Classic/Apex Lite/Apex Jr
    Replies: 1
    Last Post: 01-17-2017, 08:27
  4. Question: OSC Issues
    By Wheeler89 in forum Misc Apex Usage & Programming
    Replies: 22
    Last Post: 11-17-2014, 22:30

Bookmarks

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •