    FMM question

    I have the new ATO kit and am about to install it.
    Do I have to upgrade my system to the current version first?
    I also am thinking of installing a Neptune solenoid on my Ca reactor. Would that require a second FMM module?
    I think the answer is yes since it needs a separate 24 v powers supply.
    Thanks for your help.

  2. #2
    Frequent Contributor zombie's Avatar
    Join Date
    Dec 2013
    Location
    Denver, CO
    Posts
    13,176
    You need the most current firmware for the ATK to work properly. This is because new commands have been added such as the "When" command that acts as a maximum pump runtime latch.

    You might be an engineer if...You have no life and can prove it mathematically.

  3. #3
    Frequent Contributor zombie's Avatar
    Join Date
    Dec 2013
    Location
    Denver, CO
    Posts
    13,176
    If you want to control another 24V solenoid, You have a few options.

    1. Use a power supply and plug in an EB8 outlet (needs to be electromechanical 4 or 8, triacs might stick ON)

    2. Purchase a 1link module

    3. Purchase an EB832

    4. Purchase another FMM.

    You might be an engineer if...You have no life and can prove it mathematically.

  4. #4
    Frequent Visitor
    Join Date
    Mar 2015
    Location
    Ny
    Posts
    73
    Thanks
    If I want to use the ATO pump and 2 solenoids does that mean I'd need 3 FMM modules? Or can I run the 2 solenoids: one powered off the FMM and the other off a power strip?

  5. #5
    Frequent Contributor zombie's Avatar
    Join Date
    Dec 2013
    Location
    Denver, CO
    Posts
    13,176
    Any combination you want. A 1link gives you 2 acc ports and 3 1link ports for $150. And EB832 gives you 2 acc ports, 3 1link ports, and 8 more outlets for $250. Using a power supply will just cost you whatever the power supplies cost but you need an available outlet. Take your pick based on features you might need now or in the future and total cost.

    You might be an engineer if...You have no life and can prove it mathematically.

  6. #6
    Frequent Visitor
    Join Date
    Mar 2015
    Location
    Ny
    Posts
    73
    Great, can a 1link control AND power 2 solenoids? Or do they need separate power sources

  7. #7
    Frequent Contributor zombie's Avatar
    Join Date
    Dec 2013
    Location
    Denver, CO
    Posts
    13,176
    Yes. It can control and power them. The 1link itself has a power supply that you can just plug into a wall outlet or power strip.

    You might be an engineer if...You have no life and can prove it mathematically.

  8. #8
    Frequent Visitor
    Join Date
    Mar 2015
    Location
    Ny
    Posts
    73
    Thanks again

Similar Threads

  1. Using fmm with optical eye for auto top off with kalk question
    By jlindquist in forum Fluid Monitoring Module (FMM), FMK, ATK, LDK, and FMM Accessories
    Replies: 0
    Last Post: 09-15-2019, 07:18
  2. Question: Noob with FMM question
    By Moe103 in forum Fluid Monitoring Module (FMM), FMK, ATK, LDK, and FMM Accessories
    Replies: 1
    Last Post: 06-02-2019, 11:46
  3. Can one FMM control another FMM's ports?
    By jgann in forum Fluid Monitoring Module (FMM), FMK, ATK, LDK, and FMM Accessories
    Replies: 2
    Last Post: 10-15-2018, 11:16
  4. ATK/FMM Programming Question
    By ayaws in forum Apex Programming for Dosing, ATO, and AWC
    Replies: 2
    Last Post: 07-17-2017, 14:17
  5. FMM and Optical Sensor question
    By Andrass1989 in forum Fluid Monitoring Module (FMM), FMK, ATK, LDK, and FMM Accessories
    Replies: 0
    Last Post: 04-08-2017, 12:04

Bookmarks

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •