Hi pretty new to the Apex(classic) and have had a search about to see if there were any previous threads on this but cant find and answer, i have set up my ATK and have run the automated configuration task as a starting point, however i don't want to use the supplied ATK pump but would rather use a 12 litre per hour peri pump, plugged into one of my socket outlets
The current programming looks like this.
Fallback OFF
Set OFF
If Swx14_1 OPEN Then ON
If Swx14_2 CLOSED Then OFF
When On > 005:00 Then OFF
Defer 000:10 Then ON
Defer 000:04 Then OFF
Min Time 060:00 Then OFF
I understand i will need to extend the run time and possibly the minimum time between activation, but not sure how to utilize an out let rather than the built in pump port....hope that makes sense