When DOS is connected to a 1Link module, I know the power supply is no longer needed, but is the aquabus connection still needed?
Thanks!
When DOS is connected to a 1Link module, I know the power supply is no longer needed, but is the aquabus connection still needed?
Thanks!
1LINK carries both Aquabus and 24VDC power. You should not also connect the DŌS to your Apex system with an Aquabus cable.
Please do not send me PMs with technical questions or requesting assistance - use the forums for Apex help. PM me ONLY if the matter is of a private or personal nature. Thanks.
Thanks!
So for my already installed DOS:
1. Disconnect power
2. Disconnect aquabus
3. Connect 1Link cable
The system will continue to use the existing module names for DOS and the attahed DDR?