Ok, so I live out in the country in East Texas where if a cloud rolls in at any time and looks like rain the power goes out at any time. Most times it is short periods of 5-10 mins or just a power ON/OFF, just enough to turn off everything and come right back on. But I want to get all my bases covered.. I have read the PDF @RussM Posted and Im going by the Scenario - Ultimate setup. While most outages are short time, I want to be covered just in case it becomes a lengthy ordeal with no power for a while.
Last month I tested the limits of my Visa and it's amazing they just kept approving order after order... So, In the last month I have went from a 2 year old 70G setup to the new system all in one shot. Hey if your gonna play.. PLAY!.. I have put as much details as I can to keep from going back and answering the "WHAT IS" Questions
Rea Sea Reefer Deluxe XXL 750 Aquarium (White) 200 Gallons with 4 x AI Hydra 26 HD LED Lights
Neptune Systems 2016 APEX
2nd Neptune Systems New APEX Energy Bar 832
Neptune Systems LDK Leak Detection Kit
Neptune Systems New APEX Display Module
Maxspect XF250 Gyre on ICECAP Interface
APC 1000VA Compact UPS Battery Backup & Surge Protector, Back-UPS Pro (BX1000M)
Now the setup.. I'd like some input on coding ideas or where I may have things not just right and would work better ideas.
- From the PDF I see BLUE lines connecting the 2 EB8's and also one of the EB8s to the APEX head. I assume these are AquaBus ports connecting everything together?
- Apex 12 Volt adapter is connected to the Wall Outlet by-passing the UPS then to the APEX Head unit.
- UPS is connected to the Wall outlet
- EB832_3 is connected to the UPS for Backup (Keep running if power outage)
- EB832_2 is connected to the wall Outlet by-passing the UPS. (Non-critical if power outage)
- WIFI Router connected to a separate UPS for computer systems
- High Power draw items are separated between EB832s to divide power draw
- Considering adding a Air Pump that comes on if power is lost to add O2 to the water?
Power Consumption at FULL Power
EB832_2 Connections:
4 X AI Hydra 26 lighting = 214W 1.8A
500 Watt Heater = 725W 6.6A
GYRE XF250 Wave maker via ICECAP Interface = 22W .2A
EB832_3 Connections
GFO Reactor = 23W .2A
Carbon Reactor = 5W 0A
SUMP Lighting = 15W .1A
Return Pump = 67W .9A
Skimmer = 33W .3A
Jebao Wave makers connected direct to the UPS run on a virtual port via Interface Module
EB832_2 CODING: Plugged into Wall Outlet
HYDRA_26_2_1
Fallback OFF
Set ON
If Tmp > 82.0 Then OFF
If Power Apex Off 000 Then OFF
Min Time 001:00 Then OFF
Heater_2_4
Fallback OFF
Set ON
If Tmp > 82.0 Then OFF
Gyre_2_8
Fallback OFF
Set ON
If Output RT_PUMP_3_4 = OFF Then OFF
Defer 005:00 Then ON
EB832_3 CODING: Plugged into UPS
GFO_3_1
Fallback ON
Set ON
If Power Apex Off 000 Then OFF
CARBON_3_2
Fallback ON
Set ON
If Power Apex Off 000 Then OFF
Sump_LIG_3_3
Fallback OFF
Set OFF
If Power Apex Off 000 Then OFF
If Time 21:00 to 06:00 Then ON
If Tmp > 82.0 Then OFF
Min Time 001:00 Then OFF
RT_PUMP_3_4
Fallback ON
Set ON
If Power Apex Off 000 Then OFF
If FeedA 030 Then OFF
SKIMMER_3_5
Fallback OFF
Set ON
If Power Apex Off 000 Then OFF
If Output RT_PUMP_3_4 = OFF Then OFF
Defer 005:00 Then ON
JEBAO WAVEMAKER CODING (runs directly off the UPS)
If Power Apex Off 000 Then 30PER_FLOW
Changes to a 30% constant flow to create a turbulence at the water line for O2 exchange.