Originally Posted by
zombie
The way I recommended has a time "window" that each stage can run. The allows should be just those time windows and the defer in AllowFill is what creates the window.
The change is still permissive by the switch states so effectively it runs based on those. If you take that line out of allow fill as I recommended, what will happen is the drain will stop when either the low switch is reached or 10 minutes elapse, whichever occurs first. The Fill will start exactly 10 minutes after the drain started regardless of how long the drain was actually run for.
Sent from my SM-G965U using Tapatalk